March 6, 2024

Phase 5 Update
Road Closures Lifted

After today, March 6, Phase 5 roads will no longer experience any closures. The roads in Phase 5 are Mustang Court, Whirlaway Court, Tumbleweed Drive (after Big Range Road intersection), Big Range Road (after Hoofbeat Way intersection to Longhorn Drive south), Crusader Place, and Pecos Place. 

However, work crews will remain actively working on-site for the duration of the week, without imposing further road closures. We kindly request that residents follow posted traffic signage and work crew directions.


As always, we appreciate your cooperation and thank you for your patience during this period.

About The Pavement Improvement Project

This year’s $8.022 million dollar project consists of $7,720,000 in Board-approved funding for asphalt road reconstruction and an additional $301,790 for concrete gutter and cross gutter replacement. We will perform full-depth reconstruction on 1.4 million square feet of Canyon Lake POA-owned roads. The project will be in 10 phases and is expected to be completed by late spring 2024. We will also seal coat the 1.3 million square feet of roads reconstructed last year to ensure their longevity and effectively apply “sunblock” to them.

The funds for this project come from our well-funded Road Reserve fund, which is separate from our Repair and Replacement Reserve fund.